Permits after the fact
Manatee County code enforcement says I need a permit for work already done. What happens now?

A Manatee County code enforcement notice gives you a deadline to fix the problem. For the clients Thresh Architects has helped in Manatee County, fixing it meant a permit for the work as it stands, often called an after-the-fact permit, which took drawings of what's already built, sealed (signed and stamped) by a licensed Florida architect or engineer, then the county's zoning check (the rules for what may be built where on a lot) and plan review, then inspections, which on our jobs were done by a private provider, an inspector the owner hires. Start the permit application before the deadline, because review takes weeks, and if the deadline passes first, the case can go to the county's Special Magistrate, who hears code enforcement cases and can set daily fines and a lien, a debt recorded against the land (Manatee County).

This post is for homes in unincorporated Manatee County (outside the limits of any city or town), where Manatee County Development Services issues the permit (Manatee County). If your home is inside the City of Bradenton, Palmetto, Holmes Beach, Anna Maria or Bradenton Beach, or the Town of Longboat Key, your city's or town's building department handles it (Bradenton, Palmetto, Holmes Beach, Anna Maria, Bradenton Beach, Longboat Key). A Bradenton or Palmetto mailing address doesn't settle it: on our jobs, homes with those addresses were outside city limits and permitted by the county. Check whether your lot is inside city limits.
If you ignore the notice, daily fines can follow a hearing
The county says a case usually starts with a courtesy notice, often a door hanger, giving a deadline to correct the problem. If it passes, a formal Notice of Violation follows and the case can go to the Special Magistrate (Manatee County).
A home may then be fined $50 a day until the violation is corrected (Manatee County). State law lets the fine order be recorded as a lien. The county can't foreclose on it, meaning force a sale to collect it, if the house is your homestead, the home you own and live in (F.S. 162.09). A rental isn't protected the same way.
Code enforcement opens the case, but Development Services issues the permit (Manatee County), so your deadline can come while your plans are in review. On one of our storm repair jobs, we asked the code enforcement officer for more time, showed that the permit was under way, and the officer extended the deadline. If you need more time, ask the officer named on your notice.
Start on the permit before the deadline on your notice, because once the case reaches the Special Magistrate, the county may fine a home $50 a day.
An after-the-fact permit starts with drawings of the house as it's built

Many of our Florida clients built something, heard from code enforcement, went to the county, and were told they needed drawings of it. Most had no idea a permit for finished work meant new drawings, plan review and inspections, and they were scared. Manatee County's house permit checklist asks for, among other things (Manatee County):
- a survey signed and sealed by a surveyor
- the energy calculations form
- a soil report, for additions
- the Florida product approval number for each outside window, door, roofing and siding product
- plans signed and sealed by a registered Florida design professional, with "existing and proposed floor plans for renovations"
The plans start with as-built drawings, measured from the house as it stands. They must match it, because the private provider inspects against the approved plans. On one job where I was asked to be the private provider, the plans someone else drew showed a concrete block outside wall on a house the property appraiser lists as wood frame, so I asked for "a corrected stucco detail that matches what's actually installed."
Work built without a permit was never checked against the code, so the drawings also show the changes it requires. Our Manatee County after-the-fact jobs have been these kinds, each needing its own changes:
- garage and carport enclosures
- mobile home additions and repairs
- storm and fire repairs
- additions and second stories
- sheds and sheds turned into living space
- pools, pool cages and screen rooms
- windows, doors and stucco
The plans for work already built have to show the house as it stands, measured, before they show what must change.
You can pull the permit yourself, and you sign for the work
Florida law lets you pull the permit (apply in your own name) and act as your own contractor, called an owner-builder, when you build or improve a one- or two-family house on your own land. The work must be for your own use, "not offered for sale or lease", and you must directly supervise on site any work not done by licensed contractors (F.S. 489.103). To qualify, you must sign the permit application in person.
Manatee County's owner-builder form (Manatee County) asks for a copy of your driver license, a notarized signature or other proof the county accepts that you are the owner signing, and has you sign that you understand "as an owner-builder, I am the responsible party of record on a permit."
If you sell or rent the house, or offer to, within a year after the work is finished, the law assumes you built it to sell or rent, and the owner-builder exemption no longer applies (F.S. 489.103). A licensed contractor can file instead, though most of our Florida after-the-fact clients have filed as owner-builders.
Our clients have found the legal forms confusing, and those sent blank forms have stalled.
As an owner-builder you sign in person and become the responsible party on the permit, and if you sell or rent within a year after finishing, the law assumes you built it to sell or rent.
Record a Notice of Commencement right after you sign the application
A Notice of Commencement is a form the county clerk records to put the job on the public record (F.S. 713.13). On a contract over $5,000, Florida law has the county require a copy of the recorded notice before the first inspection, and no later inspection may be done or approved without it (F.S. 713.135). Getting the notice notarized and recorded takes time, and on after-the-fact jobs the first inspection can come quickly, since the work is already built.
As I read the law, after-the-fact permits aren't exempt. With no contract, I use the value of labor and materials on the permit application to tell whether a job is over $5,000. A single-family addition or carport enclosure almost always is, so it almost always needs the notice.
At the job, you post a certified copy, or a copy with a notarized statement that the notice was filed for recording (F.S. 713.13). The clerk charges $10 to record the first page, plus a few dollars for a certified copy (Manatee County Clerk).
Start the Notice of Commencement as soon as the permit application is signed, since on a job over $5,000 the inspections can't go on without it.
Expect review comments, and get every form right the first time
On every after-the-fact permit in our files, the county asked for at least one round of changes. The Permitting Section first checks that the application is complete (Manatee County), and on our jobs, zoning and building code reviews followed.
Once the application is complete, Florida law gives the county 30 business days to approve or deny a permit for a house under 7,500 square feet when its own reviewers check the plans, and 5 business days for a job under $15,000 on an existing house (F.S. 553.792). Each round of changes adds to that time. On our Manatee after-the-fact jobs, the whole path, from the first call to the final inspection, has usually taken about two to four months.
A wrong address on the county form naming who did each trade, such as the wiring or plumbing, and problems with the contractor's forms sent one of our jobs back to the first check for over a month. As the engineer we work with most told me, getting the forms right the first time saves weeks.
Check every form before the application goes in, because a mistake on one can send it back to the county's first check.
Our Manatee jobs have needed a private provider
On our after-the-fact permits, in the flood zone or not, the county hasn't inspected the work itself, so a private provider had to be on the permit.
For homes in the high-risk flood zone on the federal flood maps (the Special Flood Hazard Area), the county's written policy says additions and alterations "will be reviewed and inspected entirely by the Manatee County Building Division" (Manatee County). If your house is in the flood zone, ask the county at the start who will inspect your work. In my experience, the flood zone also brings the 50% rule (Manatee County): if the work costs half the home's value or more, the whole home must meet today's flood code, which an older home often can't, so it may have to come down.
The law bars a provider from inspecting a building their own firm designed (F.S. 553.791), so the provider must be a different firm from the one that drew your plans. Thresh Architects can be that provider when another firm drew your plans. We name the provider on the application from the start, because a job can stall without one. The county approved the plans on one job "pending the private provider," and another job has waited since July 2026 for one.
Under a county memo, since July 1 2026 the county takes 25 percent off the part of the permit fee for the service a provider takes over, or 50 percent off both charges when the provider does plan review and inspections (Manatee County). The provider's own fee is paid on top. The county's fee schedule also lists "Work Commencing Before Permit Issuance: 2 times the permit fee" (Manatee County). On our after-the-fact jobs, the county has charged that double fee every time.
A private provider from a different firm than the one that drew the plans has done the inspections on our Manatee jobs.
Part of a finished wall may need opening for the inspector

My firm's private provider terms say the provider "cannot inspect or certify work that is not accessible for visual examination." That can mean opening part of a finished wall or ceiling so the framing and wiring can be seen. Clients have told us they expected the inspector to sign off on the work as it stands, and were upset to learn walls had to be opened and, on one job, a beam added.
Keep the permit moving, since the county says it expires after 180 days if no required inspection has been approved (Manatee County). Once every inspection passes, the provider sends the county a certificate of compliance, stating under oath that the inspections were done (F.S. 553.791). It goes with the request for the certificate of occupancy or completion, the county's approval of the finished work.
On finished work, part of a wall or ceiling may need to be opened, because a private provider can certify only what they can see.
Sources
- Manatee County, Building Fee Schedule
- Manatee County, "Apply, Search and Manage Building Permits"
- City of Bradenton, Building and Permitting Division
- City of Palmetto, Building Department
- City of Holmes Beach, Building Department
- City of Anna Maria, "Frequently Asked Questions"
- City of Bradenton Beach, Building & Planning
- Town of Longboat Key, Building Division
- Manatee County Code Enforcement, "Code Enforcement Case Process" (Jul 29 2025)
- Florida Statutes § 162.09, fines and liens
- Manatee County Development Services, "One & Two Family Submittal Checklist"
- Florida Statutes § 489.103, owner-builder exemption
- Manatee County, "Owner-Builder" Application for Contractor Exemption and Disclosure Statement
- Florida Statutes § 713.135, Notice of Commencement before the first inspection
- Florida Statutes § 713.13, Notice of Commencement
- Manatee County Clerk of the Circuit Court, Recording Fees
- Manatee County, Permitting Section
- Florida Statutes § 553.792, permit review times
- Florida Statutes § 553.791, private providers
- Manatee County, "Private Provider Program, Projects in a FEMA Special Flood Hazard Area"
- Manatee County, Flood information
- Manatee County Development Services, "Interim Permit Fee Reductions for Private Provider Services" (Jun 25 2026)