Permits after the fact
I replaced windows, doors or stucco without a permit in Manatee County. Did I need one, and what now?

Yes: Manatee County, Florida, lists replacing windows, doors, stucco and siding among work that needs a permit, and says only minor work, such as replacing screens, painting and cleaning, doesn't (Manatee County). You can still apply for one now, an after-the-fact permit (a permit for work already done), at twice the usual permit fee (Manatee County). For windows and doors, the county's form asks for each one's Florida Product Approval number (or Miami-Dade NOA, Miami-Dade County's version of the approval), which shows the state approved that model for use in Florida (Manatee County, F.S. 553.842).

This post is for homes in unincorporated Manatee County (outside the limits of any city or town), where Manatee County Development Services issues the permit (Manatee County). If your home is inside the City of Bradenton, Palmetto, Holmes Beach, Anna Maria or Bradenton Beach, or the Town of Longboat Key, your city's or town's building department handles it (Bradenton, Palmetto, Holmes Beach, Anna Maria, Bradenton Beach, Longboat Key). A Bradenton or Palmetto mailing address doesn't settle it: on our jobs, homes with those addresses were outside city limits and permitted by the county. Check whether your lot is inside city limits.
Manatee County requires a permit to replace windows, doors, stucco or siding
Manatee County's 2026 post-storm permitting guide lists "Replacement of windows and doors," "Replacement of stucco" and "Replacement of siding" among repairs that "require a permit" (Manatee County).
The county's permit list has these permits for this work (Manatee County):
- "Door and Window."
- "Door Window Express," whose one listed document is "Florida Product Approval-NOAs." The list doesn't say whether finished work can use it.
- "Siding/Fascia/Soffit," for siding, fascia (the trim board at the roof's edge) and soffit (the underside of the overhang).
The county's fee schedule lists stucco under its siding, fascia and soffit permit (Manatee County).
Manatee County lets only minor work, such as replacing screens or painting, go without a permit.
You can still permit work already done, at double the fee
Manatee County's fee schedule lists "Work Commencing Before Permit Issuance: 2 times the permit fee" (Manatee County), and on our after-the-fact jobs the county has charged it every time. On those jobs the steps were the ones in our guide to the after-the-fact path.
In 2024 a homeowner had already taken out three old windows along one wall before getting a permit. We were hired to measure the wall and draw it as it stood, then with three new windows of the same sizes in the same places, with the owner supplying each new window's Florida Product Approval number. Even a same-size swap was drawn as the wall stood and as it would be, with each window's number.
If your contractor didn't pull the permit (apply for it), the county's window and door form is still signed by the "Contractor of record," with a license number (Manatee County), so a licensed contractor signs it, or you file as an owner-builder. Florida law lets you apply in your own name as an owner-builder, acting as your own contractor on your own one- or two-family home, for your own use and "not offered for sale or lease" (our guide, F.S. 489.103). If you file as an owner-builder and then sell or rent the home within 1 year after the work is finished, Florida law presumes the work was done to sell or rent, so the owner-builder exemption no longer covers it, and the law requires a licensed contractor to do it (F.S. 489.103).
You can still permit windows, doors or stucco already replaced, and on our after-the-fact jobs Manatee County has charged double the permit fee every time.
Each window and door needs its Florida Product Approval number
Florida law says windows, outside doors, skylights, shutters and roofing "must be approved ... before their use in construction in this state" (F.S. 553.842). Approval rests on a certification mark from an agency the state approves, a test report from a lab the state approves, or an evaluation from an evaluator the state approves or a Florida engineer or architect.
Manatee County's Door, Window & Shutter Disclosure asks, for windows and doors, whether each is impact rated (built to stand up to wind-blown debris), how many there are, and its "Product Approval (FPA or NOA number)." FPA means Florida Product Approval and NOA means Notice of Acceptance; Manatee County takes either. The county's house permit checklist asks for the number "showing expiration date" for every outside window, door and shutter (Manatee County).
As I wrote to a client, the number is "usually on a sticker on the door or in the paperwork that came with it, so a photo of the label works too," sent to whoever draws your plans. The numbers usually look like FL12345 or FL12345.1.
Find each window's and door's Florida Product Approval number, usually on its sticker or in its paperwork.
A window or door with no Florida approval or Miami-Dade NOA can be approved locally
Florida law provides for local product approval (F.S. 553.8425). A homeowner asked us about windows and a door bought overseas that had no Florida approval.
To be approved locally, the product must show it meets the code's structural windload requirements (the wind pressure it must stand up to) in one of the ways the law lists, such as a report or certification, based on testing or analysis, signed and sealed (signed and stamped) by a Florida professional engineer or Florida registered architect. If the review finds the product meets the code, "the authority having jurisdiction" (here, Manatee County's building department) "or a local building official shall deem the product approved" (F.S. 553.8425).
The county's fee schedule lists a charge for "Local Product Approval," billed by the hour (Manatee County), but no page we found says how the review works, so ask before you pay for a report. If you still have a window or door to buy, as I wrote to a client, "please ask the supplier for its Florida Product Approval number before you buy it."
Ask how Manatee County reviews local approval before paying for a report.
Plans the county approved still have to match the house

Plans the county has approved can still leave out work that was done to the house. In 2026 I was asked to be the private provider, the inspector the owner hires, on a code enforcement case, one the county opened over work done without a permit. The work was a new window, a sliding glass door swapped for a smaller swing door, new stucco, siding and soffit.
Another firm drew the plans. The county had approved the plans, waiting only on a private provider signing on to do the inspections. Before I would take the job, I compared the approved plans with photos of the house and listed 12 things to fix first.
Several were about the window and door work, and one about the wiring:
- I asked for the Florida Product Approval numbers for the new door and window "so I can confirm the installed anchoring pattern matches the anchoring detail required by the approval documentation," meaning the screws into the wall must follow the pattern each one's approval papers show.
- "The existing sliding glass door opening was larger than the new swing door," so the swap wasn't "size for size," the kind the county's form is written for. The plans showed neither the old opening nor the new wall that filled the gap, with its studs (the upright boards inside the wall) and how they were fastened to the concrete slab and the top of the wall.
- The photos showed electrical work, but no electrician was listed on the permit, and the county's form says an electrical subcontractor "is required for any electrical work" (Manatee County).
Before the inspections start, get the plans to match the house, because as private provider I inspect the work against the approved plans and each product's approval.
On a wood-frame wall, finished stucco hides most of what the code requires

Under Florida's code for houses (R703), stucco on a wood-frame wall, over its sheathing (the boards or plywood over the wall's frame), needs a water barrier at least as good as two layers of a building paper (the code calls it "Grade D paper"). Over it goes metal lath, a wire mesh the stucco grips, fastened with nails or staples at set spacing. Over block or concrete walls, the code doesn't require the paper (R703.1.1, exception 1).
At the bottom of the wall goes a weep screed, a metal or plastic strip that lets trapped water drain out, at least 4 inches above the earth or 2 inches above paving (R703). Flashing, the strips that turn water away at windows and doors, must reach the face of the finished wall or the water barrier.
On the 2026 job I checked the same parts: I wrote that "weep screed is required per the plans" and asked for photos or a visit to confirm it. Where the lath could be seen in the photos, it "appears to be stapled, which is acceptable," though I still needed to confirm its spacing. The plans showed no flashing details (close-up drawings of how the flashing is built) for the new door or window.
Once the stucco is on, the paper and lath are covered, and the weep screed at the bottom is the part still in sight. Our private provider terms say the provider "cannot inspect or certify" (sign off that it meets the code) "work that is not accessible for visual examination," so part of a finished wall may need opening (our guide).
On a wood-frame wall with finished stucco, the paper and lath the code requires are covered up, and a private provider can certify only what can be seen, so part of the wall may need to be opened.
On our after-the-fact jobs, a private provider from a different firm than the one that drew the plans has done the inspections
In my experience, Manatee County hasn't inspected after-the-fact work itself, flood zone or not, so a private provider had to be named on the permit. The county's written policy says otherwise in the high-risk flood zone, where additions and alterations to homes "will be reviewed and inspected entirely by the Manatee County Building Division" (Manatee County). There, ask the county at the start who will inspect.
The law bars a provider from inspecting a building their own firm designed (F.S. 553.791). Thresh Architects can be your provider when another firm drew your plans.
A private provider can't inspect work on plans their own firm drew.
Sources
- Manatee County, "Apply, Search and Manage Building Permits"
- City of Bradenton, Building and Permitting Division
- City of Palmetto, Building Department
- City of Holmes Beach, Building Department
- City of Anna Maria, "Frequently Asked Questions"
- City of Bradenton Beach, Building & Planning
- Town of Longboat Key, Building Division
- Manatee County Development Services, "Post-Storm Permitting Plan" (2026)
- Manatee County, Permitting Section
- Manatee County, Building Fee Schedule
- Manatee County, "Door, Window & Shutter Disclosure" (rev. Feb 26 2025)
- Florida Statutes § 489.103, owner-builder exemption
- Florida Statutes § 553.842, product approval
- Manatee County Development Services, "One & Two Family Submittal Checklist"
- Florida Building Code Online, Product Approval search
- Florida Statutes § 553.8425, local product approval
- Florida Building Code, Residential 2023, Chapter 7, Wall Covering (R703, UpCodes)
- Manatee County, "Private Provider Program, Projects in a FEMA Special Flood Hazard Area"
- Florida Statutes § 553.791, private providers