Let’s talk

Dwell Wild

Health Community Land

ThreshEarlier work of our team
Learn

Permits after the fact

I built a shed or turned one into living space without a permit in Manatee County. How do I make it legal?

Published Nov 8, 2026 · 8 min read

A shed built without a permit in Manatee County, Florida, can be made legal with an after-the-fact permit (a permit for work already built), which starts with drawings of the shed as it stands. If someone lives in it, the county counts it as a second home on the lot, allowed only when it's permitted as an accessory use (Land Development Code 401.3), such as an accessory dwelling unit (ADU), and the property's owner must live in the house or the ADU (Manatee County). Either way, the county checks on a survey (a surveyor's measured drawing of the lot) how far the shed sits from each property line, and each zoning district (a mapped area with its own rules) sets a minimum distance, called a setback.

A backyard shed made into a small home, with a front step, a window unit and its own power meter, permitted as an ADU beside the main house where the owner lives.

This post is for homes in unincorporated Manatee County (outside the limits of any city or town), where Manatee County Development Services issues the permit (Manatee County). If your home is inside the City of Bradenton, Palmetto, Holmes Beach, Anna Maria or Bradenton Beach, or the Town of Longboat Key, your city's or town's building department handles it (Bradenton, Palmetto, Holmes Beach, Anna Maria, Bradenton Beach, Longboat Key). A Bradenton or Palmetto mailing address doesn't settle it: on our jobs, homes with those addresses were outside city limits and permitted by the county. Check whether your lot is inside city limits.

A shed in Manatee County needs a permit unless it's a small prefabricated one

Manatee County treats a shed as an accessory structure, a building that serves the house, and requires a permit for one, prefabricated sheds included (the county's 2021 guide). Its permit needs building plans and a site plan (a drawing of the lot showing where each building sits) or a survey (Manatee County).

The county's 2021 guide to what needs a permit exempts only a prefabricated shed (one bought ready-made or as a kit), one used for tools or storage, as a playhouse or the like. It can cover up to 120 square feet and stand up to 8 feet high, measured to the middle of the roof's slope. Even that shed must meet the county's flood rules and its zoning (the rules for what can be built where on a lot). A shed built on site needs a permit at any size.

Before you rely on that size, check the county's newer list, from June 2026, on its permitting page.

In 2024 we made sealed (signed and stamped) drawings of a backyard storage shed an owner had built without a permit. We drew it as it stood, and our drawings showed how it stands up to Florida's hurricane winds: the walls bolted to a concrete slab and the roof strapped to the walls.

Under the county's 2021 guide, a shed needs a permit unless it's a prefabricated storage shed (one bought ready-made or as a kit) of 120 square feet or less and 8 feet high or less, and even that one must meet the zoning and flood rules.

Living in a shed is legal in Manatee County only once it's permitted, such as an ADU

Section 401.3 of Manatee County's Land Development Code allows one house on a single-family lot. A second home on the same lot is allowed only when it "is permitted as an accessory use," a use that serves the main house, such as an ADU (a small second home on the lot).

As the county's housing committee quotes the code, Section 511.18 allows an ADU only on a lot with one existing home, in the zoning districts it lists, and no bigger than 80 percent of the main house's air-conditioned area (Manatee County). The code also names two areas, Whitfield and Bayshore Gardens, where ADUs aren't allowed.

In 2025 a utility shed already turned into a small studio home came to Thresh Architects after a code enforcement case (a county case with a deadline to fix a problem). The county permitted it as an ADU in 2026. The conversion didn't make the shed any bigger on the ground, so zoning reviewed the shed where it already stood.

An ADU in Manatee County can be no bigger than 80 percent of the main house's air-conditioned area.

The owner must live on the property, and a recorded Notice to Buyer tells every later buyer

Under the county's Notice to Buyer, the owner must live in the main house or the ADU for as long as the ADU exists. The owner must show the county proof of living there when the ADU is first lived in and whenever who lives there changes.

The owner signs the notice before a notary (an official who witnesses signatures), and it's then recorded in the county's public records, so a later buyer is told. On our ADU job, the notice was recorded before the county issued the permit.

Nothing in the notice covers renting the other home, and no county page we found says whether you may, so ask the county before you rent it. Renting also matters if you pull the permit yourself (apply for it in your own name) as an owner-builder, acting as your own contractor, as the owner did on our ADU job. The owner-builder exemption covers only work for your own use, "not offered for sale or lease" (Florida law, F.S. 489.103). If you file as an owner-builder and rent or sell it within 1 year after it's finished, Florida law presumes you built it to rent or sell, so the exemption no longer covers the work, and the law requires a licensed contractor to do it.

For an ADU to be legal, the owner must live in the house or the ADU for as long as the ADU exists, and the recorded Notice to Buyer puts that on the property's public record.

Setbacks from the property lines apply to a shed too, unless the code makes an exception

A site plan with a shed in the back corner of the lot, set back from the side and rear property lines like any building, with the required yard kept clear.

Manatee County's code applies setbacks to every building and structure on the lot unless the code makes an exception, so ask the county which distances apply to your shed. The code calls the space a setback keeps clear a "required yard", and says required yards "shall apply to all buildings and structures as they relate to the lot lines," meaning the property lines (Section 401.3).

In my experience, Manatee County measures setbacks to the outside face of the wall, not the roof edge. On the 2025 to 2026 ADU, we showed the setbacks on the survey and a sealed site plan. The permit required a final survey, so a surveyor measured the shed's place again after the permit was issued.

A shed too close to a property line may have to be changed, moved or taken down. A shed that meets the setbacks but not the ADU rules can go back to being storage. Ask the county which choices fit your lot and which permit each needs. Our guide to code enforcement cases explains a case's deadlines and daily fines.

Find where the shed sits on the survey before anyone draws it, and measure to the outside face of its walls, because a shed too close to a property line may have to change or move.

A shed people live in needs what a home needs

A shed made into a place to live is permitted as a home, so the county asks for what it asks of a house (permit checklist):

  • plans sealed by an architect or engineer registered in Florida
  • the energy calculations form, which shows the building meets Florida's energy code
  • a Florida product approval number for each outside window and door, which shows the state approved the product for use in Florida

The county's 2021 guide says running power or air conditioning to a shed needs a permit. A room for sleeping must have an escape window, a window big enough to climb out of in a fire (Florida Building Code R310, as Pinellas County quotes it), and smoke alarms (a Florida Building Commission course), as our post on garage and carport enclosures explains.

For the 2025 to 2026 ADU, we drew a studio, a kitchenette, a bathroom and a storage closet. Our drawings showed a mini-split air conditioner (an indoor wall unit piped to a unit outside), insulation added in the walls, floor and ceiling, and smoke alarms wired together on the building's power, with battery backup.

The county's plan review, its check of the drawings against the code, sent them back once, and the revision added the product approval numbers for the door and window the owner kept and a storm panel (a wood panel cut to fit over the window). Every after-the-fact job in our files has needed at least one revision, so expect one, and even a door or window you keep needs its product approval number on the drawings.

A shed made into a place to live is drawn and permitted as a home, so the drawings show what the county asks of a home, such as smoke alarms, an energy form and product approvals.

In a high-risk flood zone, a large shed that isn't raised may be used only for parking or storage

A cutaway of a large shed on a slab at ground level, with flood vents in its walls and the mapped flood height drawn across it, holding only a riding mower, a kayak, tools and storage bins.

In a high-risk flood zone, Manatee County uses a Non-Conversion Agreement for a detached building over 200 square feet that isn't raised above the flood height on the map. The owner agrees to use it only for parking or storage and records that promise on the deed. Converting it needs a permit, and depending on the work, that permit may require the shed to meet the full Florida Building Code.

Find your flood zone on the county's flood page. The ADU we drew sat in flood zone X, outside the zones the county treats as high-risk, so the agreement didn't apply to it.

In a high-risk flood zone, a shed over 200 square feet that isn't raised may be used only for parking or storage, under an agreement recorded on the deed.

Inspections come last, done on our jobs by a private provider

As I've seen it, Manatee County doesn't inspect after-the-fact work, so a private provider, an inspector the owner hires, has to be named on the permit. The county's written policy says additions and alterations to homes in the high-risk flood zone "will be reviewed and inspected entirely by the Manatee County Building Division" (Manatee County). On our jobs in a flood zone, the county has checked the flood rules itself, and a private provider has still done the building inspections. In a flood zone, ask the county at the start who will inspect.

Our ADU job's permit card, the county's record of the permit, reads "PRIVATE PROVIDER PER F.S. 553.791." That law (F.S. 553.791) bars a provider from inspecting a building their own firm designed. If the shed's walls are closed in, a private provider can certify only what they can see, so part of a wall or ceiling may need opening for the framing and wiring to be inspected (our guide to the after-the-fact path).

The private provider who inspects your shed can't come from the firm that drew your plans.

Sources

  1. Manatee County, "Apply, Search and Manage Building Permits"
  2. City of Bradenton, Building and Permitting Division
  3. City of Palmetto, Building Department
  4. City of Holmes Beach, Building Department
  5. City of Anna Maria, "Frequently Asked Questions"
  6. City of Bradenton Beach, Building & Planning
  7. Town of Longboat Key, Building Division
  8. Manatee County, Permitting Section
  9. Manatee County Building & Development Services, "What Does and Doesn't Require a Permit" (2021, as posted by a local district)
  10. Manatee County Land Development Code (Municode), Sections 401.3 and 511.18
  11. Manatee County Affordable Housing Advisory Committee, "2025 Incentive Review and Recommendation Report" (quotes Section 511.18)
  12. Manatee County Building and Development Services, "Notice to Buyer, Accessory Dwelling Unit"
  13. Florida Statutes § 489.103, exemptions, including owner-builders
  14. Manatee County Development Services, "One & Two Family Submittal Checklist"
  15. Pinellas County, "2023 Florida Building Code" (emergency escape and rescue openings, Section R310)
  16. Florida Building Commission (hosted course), "Smoke and Carbon Monoxide Alarms Advanced, 2023 Florida Building Code"
  17. Manatee County Floodplain Management, "Non-Conversion Agreement" (2026)
  18. Manatee County, Flood information
  19. Manatee County, "Private Provider Program, Projects in a FEMA Special Flood Hazard Area"
  20. Florida Statutes § 553.791, private providers